The project involved remediation works to two of Seqwater’s weirs, namely Mt Crosby and Wilson Weir.
Works at Wilson Weir near Gatton involved the following:
A particularly challenging aspect of the contract was the construction of the bottom row of gabions below the water level and on the irregular river bed of the Lockyer Creek.
In order to facilitate this a coffer dam structure was constructed which allowed a binding layer of concrete to be poured to ensure a level surface for the commencement of gabion works. The construction of the gabion structures and reno mattresses to tie in with existing structures and at varying levels also required special attention to detail.
Works at the Mt Crosby Weir involved:
Each of the engineered layers mentioned above required compliance with stringent material quality specifications and in particular, a very narrow grading envelope.
In order to achieve compliance with these grading envelopes the blending of several different materials was required.
It was also vitally important that there was no difference in the grading of the material produced at the quarry to that delivered and tipped on site. Hence regular visits to the quarry to inspect stockpiles and loading operations were necessary.
Due to the steepness of the existing slope on which the engineered layers needed to be constructed, it was necessary to construct the layers horizontally and to repeatedly provide new access and departure ramps to allow for body truck movements. Measures to avoid the contamination of these layers also required attention.
The close proximity of both sites to waterways required the implementation of several erosion and sediment control measures including the use of floating silt curtains and the construction of geofabric lined sediment ponds and channels.
Water quality tests were conducted daily to ensure compliance with environmental requirements. Working close to water and on steep and unstable slopes also posed several safety risks, which through their early identification and associated implementation of risk management mechanisms ensured the safety of all employees on site.
Although plagued by an extended 2013 wet season, both contracts were completed on time and to the satisfaction of Seqwater.
Mt Crosby & Wilson Weirs
Gatton & Mt Crosby, Qld
Seqwater
September 2013
32 Weeks
$6.4 Million